Offshore Construction & Installation
Unit | Client / Location | Work Scope | Duration |
---|---|---|---|
1 |
Newfield Peninsular Malaysia Puteri Pipeline Installation, Offshore Terengganu Malaysia |
Engineering, transportation, supply of miscellaneous materials, certain pre-fabrication scope, installation and pre-commissioning of a pipe-in-pipe bundle (12″ and 8″) with a 4″ piggyback |
May 2011 – Jun 2011 |
2 |
ONGC (JV with L&T Limited) MHN Redevelopment and MHN Process Platform and Living Quarters, Offshore Mumbai, India |
Transport and installation of platforms |
Dec 2010 – May 2011 |
3 |
Integrated Transportation and Installation of Offshore Facilities (PAN Malaysia), Offshore Terengganu, Sabah and Sarawak Malaysia |
Transport & installation of platforms & pipelines |
Mar 2010 – Dec 2013 |
4 |
Carigali-PTTEP Operating Company Transportation & Installation of Platforms, Bridges and EPCIC of Inter-Field Pipelines for JDA Block B-17 Field Development, Malaysia – Thailand Joint Development Area (MTJDA) |
Transport & installation of platforms and pipelines (up to 24″ pipeline and total 48 km) |
Nov 2007 – Feb 2009 |
5 |
PETRONAS Carigali Sdn Bhd (PCSB) Transportation and Installation of Offshore Facilities, Offshore Terengganu / Sarawak and Sabah, Malaysia |
Transport & installation of platforms & pipelines |
May 2004 – Nov 2006 May 2008 – Nov 2008 May 2009 – Nov 2009 |
6 |
ExxonMobil Exploration & Production Malaysia Inc. EMEPMI Year 2007 Installation Programme, Offshore Terengganu |
Transport and installation of platforms (Jerneh B & Jerneh A) and intrafield pipelines |
Mar 2007 – Feb 2008 |
7 |
ConocoPhillips (91-12) Pty Ltd Bayu Undan Floatover, Bayu Undan Field, Timor Sea |
Floatover CUQ topside 11,500 t, DPP topside 15,000 t |
Feb 2004 |
8 |
Woodside Energy Ltd Angel Platform Topside Floatover, Angel Gas Field, Western Australia |
Engineering, construction and installation project involving transportation and installation of the Angel topside module weighing 7,700 tonnes |
Nov 2005 – Jun 2008 |
9 |
Upstream Petroleum Basker Manta Subsea Installation, Bass Strait, Victoria Australia |
Installation and diverless tie-in of various subsea flowlines and control umbilicals |
Apr 2006 – Nov 2006 |
10 |
Conoco Phillips Belanak Buoy Recovery, Natuna Sea, Indonesia |
Isolate, flush and vent riser of hydrocarbons. Disconnect risers, umbilical and mooring chains off buoy. Recover sunk mooring buoy |
Dec 2010 – Mar 2011 |
11 |
Unocal Corporation West Seno Field Development, ‘Attaka’ Field, East Kalimantan, Indonesia |
Installation north TLP complete with all facilities 8 x 26″ tension legs & 8 x TLP tendon piles. Flowlines from TLP to FPU. 2 x 12″ oil flexibles and 1 x 4″ gas flexibles |
Aug 2001 – Nov 2003 |
12 |
OMV New Zealand Limited MAARI Wellhead Platform, Taranaki Basin, New Zealand |
EPIC contract for the Maari drill ACE platform (base, support structure and process deck) weighing approx. 10,000 tonnes |
Dec 2005 – Dec 2009 |